One change order, followed from the RFI to the invoice

We follow a single change order through a job to show where the hours go, and what changes when the drafting is done for you.

Cover image for “One change order, followed from the RFI to the invoice”

·

How work changes

How work changes

·

Construction

Construction

A change order looks like one document. Behind it is a chain of small tasks spread over two or three weeks, most of them done by a project manager between other things. Here we follow one through a job to see where the hours go.

The job is a kitchen and bath remodel. On a Tuesday the framer opens an exterior wall and finds the sill plate has rotted for about six feet.

The path it takes today

The framer texts the PM a photo and a line: rot in the sill, north wall, can’t set the window until it’s dealt with. That text is the most valuable record in the whole chain, and it took him fifteen seconds.

The PM is on another site. That evening she writes the RFI to the engineer, describing what the framer found and attaching the photo. Two days pass. She calls the engineer’s office on Friday and gets the answer Monday: replace the plate and sister two studs.

Now the change has to be priced. She prices it from the framing rates in the estimate and writes the change order, with its effect on the schedule. It goes to the homeowner, who signs after a reminder.

The work isn’t finished when the signature comes back. The schedule has to move, the window installer has to be told, the budget needs the new line, and at the end of the month the invoice has to carry the change. Each is a few minutes. Each depends on her remembering it while she runs four other jobs.

The same change order in Extensar

The framer sends the same text. Nothing about his day changes.

A language model reads it, which is the step that was not possible a few years ago. It understands that the message describes a hidden condition and a hold on the window. Extensar then works from the job’s estimate and contract. It drafts the RFI against the right line of the estimate with the photo attached, and the PM reads it on her phone and sends it.

Extensar follows up with the engineer’s office, so she doesn’t have to keep it on a list. When the answer comes in, it is attached to the RFI it settles. Extensar writes the change order, priced from the estimate, and revises the schedule to match. Before the draft reaches the PM it is checked against the contract and the budget.

She reads a finished change order and decides whether it is the right one for this client. That judgment is hers. She knows the homeowner was anxious about the budget last week, so she calls before sending it.

Once the homeowner signs, the rest follows from the signature. The schedule is updated and the window installer is told the new date. The budget carries the new line. When the month’s invoice is drafted against the contract, the approved change is already on it, and it goes to her for approval.

Where the hours went

Add up the PM’s time in the first version and very little of it was judgment. Most went to writing down what the framer had already said and carrying one fact from document to document.

In the second version her time went to two things: reading the drafts and calling the homeowner. Those are the parts that needed a project manager.

The elapsed time changes too. Days in the first version were spent between steps, when the next task was waiting for someone to have a free evening. When each step is prepared as soon as the last one finishes, the change order moves at the speed of the people who have to answer.

One change order is a small thing. A mid-size contractor handles hundreds in a year, and the same chain sits behind every RFI and every pay application. That is where we think the first real gains are for a builder, well before anything changes about how a wall gets framed.

What should we cover next?

Tell us what you’re trying to figure out about AI in your work. The good questions become our next pieces.

What should we cover next?

Tell us what you’re trying to figure out about AI in your work. The good questions become our next pieces.

What should we cover next?

Tell us what you’re trying to figure out about AI in your work. The good questions become our next pieces.